Back to Docs

Roadmap

Last updated

The roadmap to 2031, set by the dates of the EHDS Regulation and its implementing acts, the EUDI and Business Wallets and Simpl-Open. The diamonds are dates set by law or by the programmes; the bars are planning windows set on 2026-11-08. P1 is due by 26 March 2027, P2 by 26 March 2029; P3 is a comment, not a build. The plan is #725.

The plan is edited in the GitHub Project: drag a bar in its Roadmap view, or change a start, a target, a priority or a status. This page draws the same plan with its notes and sources.

Every open issue belongs to an epic, a parent issue on GitHub with the work as its sub-issues. An epic's hatched bar runs from its first issue to the deadline its issues' priorities set.

The chart

  • Light bar with a blue border: planned
  • Solid blue bar: in progress
  • Red bar: blocked
  • Grey bar: done
  • Hatched bar: an epic
  • Diamond: a fixed date
  • Red line: today

Drag to pan, Ctrl or ⌘ and the wheel to zoom. Click a bar or a diamond for its details; a double click opens its issue or source. The red line is today.

What drives it

The EHDS Regulation, to 2031

Regulation (EU) 2025/327 applies in stages (Art. 105): generally from 26 March 2027, secondary use in full from 26 March 2029, further data categories from 26 March 2031. The 2026 implementing acts turn articles into specifications: dataset descriptions (2026/2098), cross-border identification and authentication of persons and health professionals, with assurance levels (2026/2099), MyHealth@EU (2026/2083).

eIDAS 2.0: the EUDI Wallet and the Business Wallet

eIDAS 2.0 obliges every Member State to offer a wallet. 2026/2099, Art. 4(2) asks, for an online request through MyHealth@EU, for electronic identification means under eIDAS at assurance level substantial from 26 March 2027 and high from 26 March 2030; it does not single out the EUDI Wallet. The German wallet d-you is to be available from early 2027. The European Business Wallet, still in negotiation, lets a person act for an organisation, as a researcher applying for a permit does.

Apache Iceberg and the lakehouse formats

Open table formats are how the large data platforms store analytical data. In the hub they belong inside the secure processing environment: OMOP as Iceberg tables behind a REST catalog, with storage credentials handed out only under a valid agreement. That is the spike #649, under #716.

Epics and items

Epic #959 · Identity and wallets

Identity and wallets: EUDI Wallet, Business Wallet, Keycloak

P1In progress2026-10-27 to 2029-03-260 of 5 done

Sign-in and attestations for citizens, health professionals and organisations: the EUDI Wallet under 2026/2099, the European Business Wallet, and the Keycloak upgrade that carries both.

Its dated items

IssueWhatPriorityStatusWindow
#708EUDI Wallet sign-in to 2026/2099Live since 2026-10-27 (ADR-065); d-you after the SPRIND sandbox registration.Identity and walletsP1In progress2026-10-27 to 2027-03-26
#709European Business Wallet: apply for a permit on behalf of an organisationADR and spike now; built once the regulation is adopted.Identity and walletsP1Planned2026-11-01 to 2027-03-26
#712Healthcare attestations and health professionals in the walletAfter #708.Identity and walletsP2Planned2027-04-01 to 2028-06-30
Open epic #959

Epic #960 · Simpl-Open

Simpl-Open interoperability

P1In progress2026-10-28 to 2028-06-300 of 8 done

The hub working with Simpl-Open: one use case end to end, the DSP compatibility kit both ways, HealthDCAT-AP as a Simpl profile, permits as bilateral contracts, and the comments on Simpl's proposals.

Its dated items

IssueWhatPriorityStatusWindow
#934One use case across two data spaces: AlphaKasse DE rewards an active yearFirst a credential from Simpl's own issuer in the IdentityHub, then a second data space; the insurer receives a yes or no, never the data (Art. 54).Simpl-OpenP1In progress2026-11-08 to 2027-03-26
#711DSP compatibility kit against a Simpl-Open connectorSimpl's code is public: release 1.0.26 builds on EDC 0.10.1, older than DSP 2025-1; step 0b of #934.Dataspace protocolsP1Planned2026-11-09 to 2027-03-26
#719HealthDCAT-AP as a profile of Simpl's DCAT-APAfter Innsbruck, which makes DCAT-AP Simpl's metadata model.Simpl-OpenP2Planned2027-01-01 to 2027-12-31
#720One Art. 68 permit, one DSP agreement per holderA permit the access body issues, carried out as bilateral contracts.Dataspace protocolsP2Planned2027-04-01 to 2028-06-30
#722Several access bodies as several Governance AuthoritiesAfter #710; the second data space of #934 is the first step.Simpl-OpenP2Planned2027-04-01 to 2028-03-31
#721The Art. 71 opt-out at the holder's connectorA person filter when data is handed over.Dataspace protocolsP2Planned2027-06-01 to 2028-06-30
#723Art. 62 fees against Simpl's monetisation modelComment on BP02E and BP14; don't build.Simpl-OpenP3Planned2026-10-28 to 2027-03-31
#724DOME: health services findable, usable only inside an SPEComment on BP02F, BP02G and SA12; don't build.Simpl-OpenP3Planned2026-10-28 to 2027-03-31
Open epic #960

Epic #961 · Permits and processing

Secondary use: permits, secure processing, opt-out and audit

P1Planned2026-11-08 to 2029-03-260 of 11 done

Secondary use as it runs: applications and permits, the secure processing environment, the Art. 71 opt-out, the policies the connector enforces, and the audit trail that proves it.

Its dated items

IssueWhatPriorityStatusWindow
#649Spike: Apache Iceberg tables with a REST catalog inside the SPEGravitino or Polaris; credentials vended only under a valid agreement. Sub-issue of #716.Permits and processingP2Planned2026-11-01 to 2027-02-28
#716Art. 73 secure processing environment: a workspace per permitResults leave only after review.Permits and processingP2Planned2027-03-01 to 2029-03-26
#717Applications: Art. 53 purposes, Art. 81 complaints, Art. 70 templatesTemplates after their implementing act.Permits and processingP2Planned2027-03-26 to 2028-09-30
#204Sealed data permits as credentialsUsed by #709 and #720.Dataspace protocolsP2Planned2027-07-01 to 2028-09-30
Open epic #961

Epic #962 · Health standards

Health standards and the dataset catalogue

P1Planned2026-11-08 to 2029-03-260 of 13 done

FHIR, OMOP and HealthDCAT-AP: dataset descriptions to 2026/2098, the EU catalogue and HealthData@EU, the exchange format, lab reports and the federated catalogue.

Its dated items

IssueWhatPriorityStatusWindow
#714Art. 79: publish the catalogue for harvestingThe EU dataset catalogue reads HealthDCAT-AP.Health standardsP2Planned2027-01-01 to 2027-12-31
#713Art. 75: a national contact point adapter over eDeliveryAfter the HealthData@EU implementing act.Health standardsP2Planned2027-03-01 to 2028-12-31
#715Art. 78: the quality and utility label in the metadataIn the dataset description.Health standardsP2Planned2027-06-01 to 2028-06-30
#718Art. 7 portability on the HL7 Europe guidesFHIR in the European exchange format.Health standardsP2Planned2027-09-01 to 2028-12-31
Open epic #962

Epic #963 · Dataspace protocols

Connector platform: EDC 1.0 and the data planes

P1In progress2026-11-08 to 2029-03-263 of 12 done

The connector the dataspace runs on: the move to EDC 1.0, the data planes, the TCKs and the protocol versions, retiring EDC 0.18, and CFM as eclipse-cfm releases.

Open epic #963

Epic #964 · Klarbefund and patient record

Klarbefund and the patient's own record

P2Planned2026-11-08 to 2029-03-260 of 5 done

The Klarbefund app and what a person brings into their record: sign-in from the patient screen, scanned lab values, Apple Health trends, and the evidence for a pilot.

Open epic #964

Epic #965 · Security and operations

Security, operations and cost on Azure

P1In progress2026-11-08 to 2029-03-261 of 10 done

Running the hub safely and affordably: secrets and the database firewall, the NLQ's read-only session, Keycloak load, logs, traces and alerts, and the load tests.

Done
#577
Open epic #965

Epic #966 · Quality and CI

Quality: tests, CI and documentation

P1In progress2026-11-08 to 2029-03-261 of 6 done

Checks that can fail and say why: the end-to-end tests, API checks that pass on an empty answer, CI minutes and CodeQL, and the developer manual.

Done
#951
Open epic #966

Epic #967 · Demos and partners

Demos and national profiles

P2Planned2026-11-08 to 2029-03-260 of 2 done

Showing the hub to access bodies and national programmes, and what a multilingual demonstrator with national implementation profiles would take.

P2
#27
Open epic #967

Epic #990 · EHDS regulation

TEHDAS2 results: what the hub implements, and the final conference demo

P1In progress2026-11-08 to 2029-03-263 of 13 done

The Joint Action's guidelines checked against the hub requirement by requirement, published under /docs, and shown at its final conference on 16 November 2026.

Its dated items

IssueWhatPriorityStatusWindow
#991TEHDAS2: the high-relevance results checked requirement by requirementDone 2026-11-09: three of six ratings corrected (ADR-086), the gaps filed as #1029 to #1033.EHDS regulationP1Done2026-11-09 to 2026-11-13
#992D6.4 DAAMS: the application and permit model against the specificationDone 2026-11-09: 31 of 94 elements the same, 33 different, 30 missing; the permit lifecycle is #1031.Permits and processingP1Done2026-11-09 to 2026-11-13
#994TEHDAS2 final conference: the demo along its four sessionsBrussels and online on 16 November 2026; a rehearsal on 13 November, the static site as fallback.Demos and partnersP1Planned2026-11-10 to 2026-11-16
#993The TEHDAS2 mapping as a page under /docsDone 2026-11-09: /docs/ehds/tehdas2-mapping, the one link the demo hands out.EHDS regulationP1Done2026-11-11 to 2026-11-15
#995Citizen Information Point without sign-inNeeds an ADR that supersedes ADR-044 for the information page.EHDS regulationP2Planned2026-11-10 to 2026-12-18
#997TEHDAS2 wave 3: the seven guidelines re-rated on their final versionsNone of the seven was final on 9 November 2026.EHDS regulationP2Planned2026-11-17 to 2026-12-18
#996D8.2 significant findings: assessed by the access body, told to the personNot covered yet: only the policy duty to report an incident exists.Permits and processingP2Planned2026-12-01 to 2027-03-26
Open epic #990

Closed before the epics

Done before every open issue was given an epic on 2026-11-08.

IssueWhatPriorityStatusWindow
#694The adopted article numbers and the 2026 implementing actsClosed 2026-10-27.Health standardsP1Done2026-10-01 to 2026-10-27
#700HealthDCAT-AP Release 8, valid against the official shapesOn Azure since 2026-10-28 (ADR-063).Health standardsP1Done2026-10-13 to 2026-10-28
#710Trust a Simpl Governance Authority as a credential issuerClosed 2026-10-28: a fictional Governance Authority, trusted for its own credential types only (ADR-064, decision 2, TRUST-6.1 to 6.5).Simpl-OpenP1Done2026-10-27 to 2026-10-28